Bidders get broadband breather

Fibre network delayed by three months

Australia's $8 billion National Broadband Network (NBN) has been set back for at least another 12 weeks, after the government bent under pressure to extend the tender October deadline.

Communications Minister Stephen Conroy has long been criticised for not supplying enough information for bidders to construct sufficient plans to build the network.

Members from Telstra and the Optus-led Terria consortium, formally the G9, now have slammed the Fibre-to-the-Node (FttN) tender documents and labeled them "watery" and insufficient.

Specifically industry argues that the documents do not provide data on Australia's telecommunications infrastructure, or the pricing and regulatory environment in which the winning bidder will have to operate the network.

Conroy successfully passed a bill to safeguard sensitive network information held by infrastructure owners including Telstra and PIPE networks, after the companies refused in Februrary to supply the data to government.

The opposition failed to squeeze amendments into the bill to force the government to reveal more information about the NBN environment, including architecture, and wholesale access models.

Contenders will have 12 weeks to place a bid from the time "all material is made available" to the tender documents.

Ovum director David Kennedy said he is not surprised of the deadline extension.

"The government has been pushing too hard to meet a political timetable," Kennedy said.

"The Government should aim for the right result, not a quick result.

"A few extra weeks to ensure that the process is genuinely competitive are well worth any additional delay."

Shadow communications minister Bruce Billson has lodged a complaint with the Auditor General regarding the tender process.

Join the newsletter!

Error: Please check your email address.
Rocket to Success - Your 10 Tips for Smarter ERP System Selection
Keep up with the latest tech news, reviews and previews by subscribing to the Good Gear Guide newsletter.

Darren Pauli

Computerworld
Show Comments

Most Popular Reviews

Latest Articles

Resources

PCW Evaluation Team

Ben Ramsden

Sharp PN-40TC1 Huddle Board

Brainstorming, innovation, problem solving, and negotiation have all become much more productive and valuable if people can easily collaborate in real time with minimal friction.

Sarah Ieroianni

Brother QL-820NWB Professional Label Printer

The print quality also does not disappoint, it’s clear, bold, doesn’t smudge and the text is perfectly sized.

Ratchada Dunn

Sharp PN-40TC1 Huddle Board

The Huddle Board’s built in program; Sharp Touch Viewing software allows us to easily manipulate and edit our documents (jpegs and PDFs) all at the same time on the dashboard.

George Khoury

Sharp PN-40TC1 Huddle Board

The biggest perks for me would be that it comes with easy to use and comprehensive programs that make the collaboration process a whole lot more intuitive and organic

David Coyle

Brother PocketJet PJ-773 A4 Portable Thermal Printer

I rate the printer as a 5 out of 5 stars as it has been able to fit seamlessly into my busy and mobile lifestyle.

Kurt Hegetschweiler

Brother PocketJet PJ-773 A4 Portable Thermal Printer

It’s perfect for mobile workers. Just take it out — it’s small enough to sit anywhere — turn it on, load a sheet of paper, and start printing.

Featured Content

Product Launch Showcase

Latest Jobs

Don’t have an account? Sign up here

Don't have an account? Sign up now

Forgot password?